Build Sequence

Wall panel installation

How to approach wall panels, splines, glue, fixing, temporary bracing, and alignment.

Approx 11 min0 / 9 lessons complete0% progress

Sequence and bracing

Wall panels should be installed in the sequence shown on the drawings or schedule. Brace as you go so panels stay plumb and safe before the roof structure ties everything together.

Corners and openings need particular care. Check that panels are plumb and square before permanent fixing.

Joints and fixings

Apply adhesive and fixings as specified. Missed glue lines or inconsistent fixing spacing can create movement, air leakage, and weak points.

Clean excess adhesive where needed, but do not remove material that is forming the required bond line.

Before you move on

  • OKBrace walls before releasing lifting support
  • OKCheck plumb at each corner and opening
  • OKConfirm fixings before covering joints