Standard Details (SD)

SD-22: Partition Head Connection (Perpendicular to Joists) — Steel Beam

Head detail when a steel beam is present; check downstand depth and fixing zones.

Duration: 6 minLevel: Details
SD-22: Partition Head Connection (Perpendicular to Joists) — Steel Beam

SD-22: Partition Head Connection (Perpendicular to Joists) — Steel Beam

What this detail covers

  • Partition head connection where a steel beam runs through the floor zone.
  • Blocking and fixing zones around the beam to match the specification.

Key steps

  1. Confirm engineered beam size (especially downstand depth) and pocket clearances.
  2. Install blocking as shown to create a fixing zone for the partition head.
  3. Fix to specification and maintain any required movement allowance.

Checks

  • Beam size and downstand depth confirmed before framing (avoid clashes).
  • Fixings installed to spec and into the intended blocking zones.

Common mistakes

  • Framing before confirming the actual beam depth.
  • Fixing into thin/unsupported deck edges instead of the specified blocking.

Indicative only: always follow the engineer’s fixing schedule and the project drawings.

Ready to build your own kit specific to your project?

Explore SIP kit options and choose the build type that fits your brief.

View kit options

Finished this lesson?

Mark it as complete to track your progress towards becoming a SIP expert.