What this detail covers

  • Fixing an internal partition at the head where joists run perpendicular.
  • Maintaining the required gap/allowance so the floor can deflect without cracking finishes.

Key steps

  1. Confirm whether the partition is loadbearing or non-loadbearing (this affects the head detail).
  2. Set the partition line and maintain the specified deflection gap (often shown as ~15mm).
  3. Install the head fixing as shown and to the specified schedule.

Checks

  • Deflection gap is present and consistent along the run.
  • Fixings do not “hard lock” the partition to the floor structure unless designed to.

Common mistakes

  • Filling the deflection gap with rigid materials, causing cracks later.
  • Using a generic head fixing without checking the joist direction/detail intent.

Indicative only: always follow the engineer’s fixing schedule and the project drawings.

Ready to build your own kit specific to your project?

Explore SIP kit options and choose the build type that fits your brief.

View kit options

Finished this lesson?

Mark it as complete to track your progress towards becoming a SIP expert.